Schedule Madness

Some day the boss will die, be promoted, or quit. Between now and then, you'll need to find a better way to do scheduling.

An inhabited planet appears on the forward sensor array, the first in this sector. Monitoring strange teleradio chatter-mostly entities being unbearably unkind to each other on something called Jerry Springer and paranoid ballistic missile radar-we learn that this place is called Earth. The scanners zoom in. On the display, continents resolve into cities, rivers into estuaries, R & D parks into individual buildings. Roofs are transparent to the sensor beam; we home in until our point of view is over the shoulder of a worker-entity hunched over a keyboard and screen. Closer in, we see a single open window on the cathode ray tube, something labeled “Microsoft Project.”

A mouse dances furiously in the worker's hand, moving triangles around in a blaze of motion even our quad eyestalks can barely follow. Oddly, the last triangle on the screen-something labeled “ship date”-stays put.

Ah, now we understand. This is a computer game of some sort. The object seems to be to make lots of complicated interrelated events happen in a fixed time. A variant of chess perhaps. The entity's mutterings seem to confirm this idea as we listen in. It seems the enemy is a dark force named “management.” Listening more intently, we learn that the goal is to convince the opposing generals that the game can be completed in a time-frame they've fixed. Things get spicier during the enemy's turn, when they'll sometimes arbitrarily decrease the allotted project time.

What an odd game! We turn to each other, shrug, neither of us understanding how either side could be having fun. Perhaps all of these entities are as cruel to each other as we saw on that Jerry Springer broadcast.

This seems more an exercise in frustration than gaming thrills. Humans-they're so hard to understand. We decide to abandon Earth and return to Epsilon Theta IV, where the Bzorkians long ago evolved beyond such petty conflict.

Dysfunctional scheduling

The proliferation of personal computers in the early '80s caused a frenetic search for the post-spreadsheet “killer app.” For a while it seemed that project management (PM) software might fill that niche. Those dreams faded, though these software packages have come to form a basic part of most developers' toolkits.

In the days before PMs, creating and maintaining schedules was a nightmare. It was like writing code in hex instead of assembly; every little change meant manually moving all timelines and task dates around. PM software was clearly a boon to managers.

Or was it? I can't fault the PM apps themselves, but almost without exception it seems that people use these tools in entirely dysfunctional ways. In my experience, the vast majority of engineers scheduling a project start with a capriciously imposed deadline (the end date) whose location on the timeline is fixed. That triangle is somehow anchored in place by forces that go far beyond reason and reality.

With a locked-in end date the rest of the scheduling process seems aimed at making a plan that's believable, rather than one that's right. “Yeah, sure this looks good; better give that task a week, which leaves only three days for integration; I guess that'll work.”

No, actually. Scheduling a project this way will not work. Ever.

When properly used, PM software lets us decide how tasks interrelate, so we can identify and optimize critical paths before starting the project. It shows just how long each event line will take, ultimately giving us a reasonable prediction about development time. Without sheer luck, in the form of a generous end date, working backward from a fixed time is doomed to failure.

In my opinion, we waste our time creating a schedule meant to hit a mandated ship date. We're engaging in the art of creative lying, trying to contort the facts into a deceit aimed at making the boss happy now, and deferring the consequences. It's like the kid who hides the report card until Monday so the parents won't ruin his weekend. There will be hell to pay, but we do our best to delay the consequences as much as we can.

Inadequate designs

Imposed ship dates are only part of dysfunctional scheduling. For decades, software gurus have taught us the right ways to build programs, but too often these sages are so shielded by the forgiving arms of academia that what they preach is simply impossible for those of us in the trenches to use. Not that they are wrong, just impractical.

For example, the philosophy behind traditional estimation schemes is that size is an accurate predictor of the resources and time needed to develop a product. At the risk of gross simplification, most scheduling methods convert software size (measured in some variant of lines of code or function points) to person months. For example, Boehm's COCOMO model predicts time by an equation of the form:[1]

Time = constant * (thousands of source lines)exponent

COCOMO and its derivatives go to great lengths to define the constant and exponent, which are each functions of many other characteristics of the project. Often glossed over is the critical variable: the size of the program in lines of code (or function points, or any of a dozen other measures). How many of us know this value to any degree of certainty when creating a schedule?

It seems to me that two factors in particular make estimating a project's size problematic. The first is obvious: we do it badly. Under the best of circumstances it's very hard to come up with a correct, or even close, size estimate. In my experience, most folks underguess by a factor of about two. That's a tremendous error, and would be intolerable in any other business endeavor. For instance, a healthy company might run a 10% profit margin. An error costing just 5% of the business's gross revenues slashes profits in half. Errors of 10% yield losses and layoffs. Only dot-coms can afford (or at least tolerate in some mysterious manner) the 100% error rates we routinely experience.

The second problem is that only rarely do the developers have a chance to create an accurate estimate. Let's face it, when the boss wants a schedule he wants it today; or tomorrow; end of the week at the latest. Yet an honest size approximation requires a fairly complete system design, which might take weeks or even months.

The boss wants to know a ship date, generally with a margin of error approaching zero, and gives us an impossibly short deadline to come up with one. Is it any surprise that so many embedded systems are delivered late?

Yet the boss might be responding to pressure from above. To determine if a product idea is profitable it's important to know when it will be released and how much the engineering will cost. It's hard for him to justify spending months and lots of money creating a system design when he's only interested in a cost number for trading-off business issues.

One approach is a best-guess estimate created in the time allowed, but mediated by broad error bands. “Give us six months, minus two plus eight.” Unhappily, as illustrated in several Dilbert cartoons, the boss usually hears “probably four months, no more than six.”

A final problem is poor product specifications. As a young engineer my boss once said to me: “Let's do a new Product X. Just like the last one, but smaller and faster. More accurate, too. How long will it take?” The sound of my jaw crashing to the floor barely fazed him. My estimate was about as precise as his product definition. It's hard to create a comprehensive spec, and it often takes more time than the boss cares to invest just for the sake of scheduling.

So we have assembled all the elements of disaster:

  • The specification we start with might be inadequate or practically non-existent.
  • We have too little time to do the real design needed to create a meaningful completion date.
  • Future viability of the product, and perhaps the company as well, depends on us getting both the schedule and the product right.
  • The boss does not want to hear the truth.

The quixotic schedule dance that goes on between developers and managers takes an even more dysfunctional dive when the capricious end date is set to meet a big show or conference. The show. Aren't you sick of hearing about the show, and how the product simply must be ready for demos by then? The boss seems to think that missing that date means utter doom; the competition will introduce their product, ultimately prevailing in the industry. Or this is the only chance we have to get the press needed to make that big splash the marketing folks demand.

A show is always looming, one whose importance to the company gets trumpeted with ever-increasing frenzy as its date nears.

I'm not discounting the importance of shows and of marketing, but it bothers me that we ignore the truth behind show demonstrations. As a result, we create an impossible deadline, and, in all likelihood, deliver a horribly flawed product.

Go to the show. Watch the attendees strolling along the floor. Stop at a few booths and see how the salespeople put the product through its paces. That demo might last 10 seconds-Fifteen tops!

Even more enlightening, get an exhibitor's badge and visit the show floor the day before the exhibits open, during booth set-up. There's nothing more fascinating than watching the salespeople removing bubble wrap from the latest new product. Their eyes are full of terror, terror induced by too much experience showing products that are not ready. So many defects, so many system crashes; the best sales folks are those with hides so thick that no bug-induced failure creates the least embarrassment.

It seems to me that the show needs a product that demos reliably, and that passes the 10-to-15 second test. You don't need 50 functioning features. It's far better to extract the few truly important parts of the product, and design and test those so they're perfect.

A realistic schedule represents the show as one deliverable among many; one with a few “wow” features that are utterly reliable.

Alternatives

One substitute to the conventional design-and-schedule-it-all-up-front approach is to develop incrementally. Start building the system based on your current understanding of the requirements and design trade-offs, but continually refine both the design and the schedule. Issue intermediate releases, which all asymptotically approach the final desired product and give stakeholders a chance to see how the product works.

As we proceed from requirements to design to coding to test, the schedule estimate will grow more precise with narrower error bands. A 100% uncertainty at the outset will shrink once the specs are understood, the risks are identified, and things start working.

Incremental development might be the most honest way to build a product, because it acknowledges that the spec will be faulty, the design flawed, and that only through the process of actually making the thing will we figure out what we're doing. These truths may be ugly, but they're inescapable.

But how many managers are willing to tolerate the uncertainty of such a process? “Whaddaya mean the schedule's gonna keep changing? I need an accurate number before we start!” I think that if we combine incremental development with an initial fuzzy estimate bounded by error bands we'll be as accurate as we're likely to be. But few bosses seem willing to proceed without a hard and fast delivery date, even when we all know that date is set in quicksand.

Instead, we participate in a mutual delusion dialog, settling for an agreeable but clearly outrageous plan.

Destiny

A wise man once told me everything I need to know about my destiny. Some day I'll die. Between now and then everything else is up to me.

So too with bosses. Some day the boss will die, or be promoted, or quit, or move to sales (rather like dying, I suppose). At some point you'll find yoursef in the leader's role. You'll be the one tempted to impose an arbitrary ship date, or give inadequate design time.

What action will you take at that point? Can you resist the pressure from the CEO, shareholders, and customers and do things right? Or, will you cave to the overwhelming forces that drive people to management by fiat?

It's up to you.

Jack G. Ganssle is a lecturer and consultant on embedded development issues. He conducts seminars on embedded systems and helps companies with their embedded challenges. He founded two companies specializing in embedded systems. Contact him at .

References

1. Boehm, Barry. Software Engineering Economics. Englewood Cliffs, NJ: Prentice-Hall, 1981.